On-vehicle InspectionON-VEHICLE INSPECTION PROCEDURE 1. INSPECT PTC HEATER RELAY(PTC HTR NO. 1, NO. 3) (a) Measure the resistance according to the value(s) in the table below. Standard Resistance: Tester Connection Condition Specified Condition 3 - 5 Auxiliary battery voltage is no
INSTALLATION PROCEDURE 1. INSTALL NO. 2 ECM BRACKET (a) Install the No. 2 ECM bracket to the ECM with the 2 screws. Torque: 3.0 N·m {31 kgf·cm, 27 in·lbf} 2. INSTALL NO. 1 ECM BRACKET (a) Install the No. 1 ECM bracket to the ECM with the 2 screws. Torque: 3.0 N·m {31 kgf·cm, 27 in·lbf} 3. IN